Liquidated damages clause in aircraft purchase agreement not an unenforceable penalty
Related people
10 May 2021
The claimant aircraft manufacturer claimed damages under an aircraft purchase agreement for the non-payment of pre-delivery payments (PDPs) following the defendant’s failure to pay the PDPs and to take delivery of a number of aircraft. The court granted summary judgment in favour of the claimant, and found that the liquidated damages clause in the agreement was not an unenforceable penalty: De Havilland Aircraft of Canada Ltd v SpiceJet Ltd [2021] EWHC 362 (Comm)
The defendant entered into an aircraft purchase agreement with the claimant, under which it agreed to buy 25 aircraft. The defendant paid for and took delivery of the first five aircraft, but failed to pay the PDPs in respect of the remaining aircraft and failed to take delivery of the next three aircraft that were due to be delivered.
As a result, the claimant terminated the purchase agreement and, in reliance upon a liquidated damages clause, sought damages in respect of all of the undelivered aircraft for USD42.95m.
The claimant sought summary judgment.
The defendant raised three main defences:
- The defendant’s obligation to pay the PDPs had been suspended by agreement.
- The claimant was in breach of its contractual obligation to assist the defendant in arranging finance and such breach rendered the defendant’s compliance with its contractual payment obligations impossible.
- The liquidated damages clause contained in the purchase agreement amounted to an unenforceable penalty.
Suspension of the obligation to pay the PDPs
The defendant argued that its contractual obligation to pay the PDPs for the undelivered aircraft had been suspended due to the wording used in a later document, Change Order 6 (CO6), which amended the terms of the purchase agreement. CO6 provided that the Scheduled Delivery Months for aircrafts 9-25 would be suspended and that the parties would make good faith efforts to agree a delivery date in the future.
The defendant argued that the way the purchase agreement was drafted meant that the liability for payment of the PDPs was linked to a specified Scheduled Delivery Month (as they were prescribed as being due a certain number of months prior to the Scheduled Delivery Month) and therefore if the Scheduled Delivery Months had been suspended, so had the obligation to pay the corresponding PDPs. The defendant argued that it did not make business sense for it to pay for aircraft when there was no agreement as to when they would be delivered.
The judge held there should be summary judgment for the claimant on this issue because, inter alia, CO6 expressly provided that all terms of the purchase agreement would remain unchanged and would continue to be binding on the parties. The judge was also persuaded by the claimant’s argument that there was a long stop date of August 2023 for delivery of the aircraft, so the PDP payment was not suspended indefinitely and the claimant remained under an obligation to manufacture and deliver the aircraft, and so required the security of the PDPs to do so.
The claimant’s obligation to provide assistance in arranging finance
The defendant also sought to argue that the claimant was in breach of its contractual obligation to assist in arranging finance for the PDPs and this breach rendered the defendant’s compliance with its payment obligations impossible.
The judge, again finding for the claimant, held that due to the wording of this provision, any assistance given by the claimant would have been very limited and, even if the claimant was obliged to do something more than just consult with third parties and the defendant to develop financing procedures, the obligation was too uncertain to be enforceable. Therefore, it was not arguable that a breach of this obligation could amount to a defence to non-payment of the PDPs. The judge also drew attention to the fact that the defendant’s arguments were inconsistent with the terms of the purchase agreement, which provided that all of the defendant’s payments thereunder were unconditional.
Penalty clause
Finally, the defendant argued that the liquidated damages clause in the purchase agreement was an unenforceable penalty clause and unsuitable for determination on a summary basis because more evidence of the factual matrix was needed to assess the reasonableness of the bargain reached. This included the price of the aircraft and the regularity with which liquidated damages clauses are used in the industry. Further, the defendant pointed to the fact that no evidence had been adduced by the claimant quantifying the maximum conceivable loss suffered in respect of each aircraft (in breach of the fourth proposition set out by Lord Dunedin in Makdessi v Cavendish).
In response, the claimant argued that no evidence is required as to the actual loss suffered as that would subvert the purpose of the liquidated damages clause, which was to avoid having to go through the time and expense of proving the actual loss suffered. The judge agreed with the claimant, noting that the defendant had not been able to cast doubt on the liquidated damages figure in the purchase agreement, which had been agreed by the parties at the time, and therefore the liquidated damages clause was not an unenforceable penalty.
Comment
This decision highlights the importance placed by the courts on the bargain reached by the parties at the time the contract was entered into, particularly with regard to liquidated damages clauses. It also reinforces the importance of ensuring that any contractual obligations are drafted in such a way as to provide certainty and shows the continued importance of hell or high water clauses within contracts.
The defendant has appealed and the hearing is currently listed for Spring 2022.
Further information
This case summary is part of the Allen & Overy Litigation and Dispute Resolution Review, a monthly publication. If you wish to receive this publication, please contact Amy Edwards, amy.edwards@allenovery.com