Skip to content

MEMR 16/2019: a ray of sunshine for Indonesia’s rooftop Solar PV industry

Related people
Michael Tardif

Foreign Legal Consultant (partner level), Ginting & Reksodiputro in association with Allen & Overy

Jakarta

View profile →

Afkar Ferhat
Ferhat Afkar

Senior Associate, Ginting & Reksodiputro in association with Allen & Overy

Jakarta

View profile →

Bessendorf Ari
Ari Bessendorf

Foreign Legal Consultant, Ginting & Reksodiputro in association with Allen & Overy

Jakarta

View profile →

25 October 2019

New MEMR regulation has reduced the capacity charge that has hindered installation of behind the meter rooftop solar photovoltaic projects.

On 23 October 2019, the Minister of Energy and Mineral Resources (MEMR) published Regulation No. 16 of 2019 (MEMR 16/2019), amending Regulation No. 49 of 2018 on the Use of Rooftop Solar Power Generation (MEMR 49/2018). MEMR 16/2019 reduces capacity charges and eliminates the emergency energy charges payable to PLN for on-grid industrial consumers who use behind the meter solar rooftop photovoltaic power plants (Solar PV), which will lead to better project economics for Solar PV.

PLN requires that industrial customers pay a capacity charge and emergency energy charge if installing on-grid, behind the meter generation. Regulation No. 1 of 2017 on Parallel Operation of Power Plants with Power Grids of PLN (MEMR 1/2017) set out the formula for the calculation of the capacity charge:

Capacity Charge = total Net Power Capacity of plant (MW) x 40 hours x electricity rate

This capacity charge applied to all industrial consumers (Industrial Users). For Solar PV, this calculation was cost prohibitive and significantly damaged the economics of such projects, as Solar PV projects, unlike thermal generation, only generate power when the sun is shining.

MEMR 49/2019 was potentially inconsistent with respect to the applicability of capacity charges to Solar PV. Article 17 of MEMR 49/2019 provided that MEMR 1/2017 no longer applied to Solar PV Industrial Users. However, Article 14(2) of MEMR 49/2019 provided that Solar PV Industrial Users are subject to capacity charges and emergency energy charges.

In practice, MEMR’s view was that MEMR 1/2017 still regulated capacity and emergency energy charges for Solar PV Industrial Users. With MEMR 16/2019, MEMR has now provided regulatory certainty to such Industrial Users, and made the capacity charges proportional to Solar PV generation.